RHP beneficiaries - refugees and internally displaced persons - have the choice of either voluntary return and reintegration in their place of origin or integration in their place of current residence. The beneficiaries are provided with the most suitable housing modality based on their needs and family profile. These modalities include the construction of apartment buildings; the reconstruction/renovation of buildings or houses; the provision of building material packages; the provision of pre-fabricated houses and the purchase of apartments or village houses.

Construction of Apartment Buildings and Purchase of Apartments

Construction of multi-apartment buildings and purchase of apartments is best suited for beneficiaries who wish to re/integrate in the urban communities.

Sub-project / Component Number of apartments Completion date
BiH3 / C1 8 2nd half of 2017
BiH3 / C2 178 2017-2018
BiH3 / C3 252 1st half of 2018
Sub-project / Component Number of apartments Completion date
HR1 29 Completed
HR2 40 1st half of 2017
HR3 75 2nd half of 2017
HR4 101 2nd half of 2017
HR5 21 1st half of 2017
Sub-project / Component Number of apartments Completion date
MNE1 62 Completed
MNE2 171 2017-2018
MNE3 68 2nd half of 2017
MNE4 94 1st half of 2018
Sub-project / Component Number of apartments Completion date
SRB2 / C1 200 2nd half of 2017
SRB3 / C1 235 2nd half of 2017
SRB4 / C1 261 1st half of 2018
SRB5 / C1 1262 1st half of 2018

Provision of Building Material Packages

Distribution of building material packages is the most appropriate modality to support such beneficiaries who have already started the re/construction of their family houses.

Sub-project / Component Number of households Completion date
BiH1 / C1 20 2nd half of 2016
Sub-project / Component Number of households Completion date
SRB1 / C2 129 2nd half of 2016
SRB2 / C3 300 2nd half of 2017
SRB3 / C3 350 1st half of 2018
SRB4 / C3 562 1st half of 2018
SRB5 / C2 250 1st half of 2018

Provision of Pre-fabricated Houses

Pre-fabricated houses are an efficient solution designed for beneficiaries who already own their construction plot.

Sub-project / Component Number of pre-fabs Completion date
SRB1 / C1 64 2nd half of 2016
SRB2 / C2 120 2nd half of 2017
SRB3 / C2 80 2nd half of 2017
SRB4 / C2 81 2017-2018

Re/construction of Houses

Re/construction of houses is the most suitable modality for beneficiaries who decide to either return to their place of origin or integrate in the local community.

Sub-project / Component Number of houses Completion date
BiH1 / C1 51 2nd half of 2016
BiH1 / C2 99 2016-2017
BiH2 / C1 30 1st half of 2017
BiH2 / C2 750 2nd half of 2017
BiH4 / C1 250 2nd half of 2017
BiH4 / C2 170 2nd half of 2017
BiH4 / C3 15 2nd half of 2017
BiH4 / C4 45 2nd half of 2017
Sub-project / Component Number of houses Completion date
HR6 62 2nd half of 2017

Purchase of Village Houses

Village houses are purchased for beneficiaries usually living in rural areas who plan to make a living from agriculture.

Sub-project / Component Number of houses Completion date
SRB2 / C4 250 2nd half of 2016
SRB3 / C4 69 1st half of 2016
SRB4 / C4 329 2017
SRB5 / C3 200 2nd half of 2017